DCVA Installation Guide
This Document serves as a guide for the installation of an DCVA inside the boundary of Water District #20. All installations must be inspected and approved by the Districts Cross-Connection Control Specialist. Please contact the District within 2 business days to schedule an inspection.
​
-
Assembly shall be installed on the customers side of the meter prior to any branch or tee on the service line.
-
A DCVA shall be installed in the orientation for which it is approved.
-
Install Assembly according to the manufacturers specifications.
-
Assembly must be installed in an enclosure (In ground or above ground).
-
Water District #20 highly recommends freeze protection. (Insulation or padded wraps
-
Installed Assembly shall be rigid and stable
-
Installed Assembly should be easily accessible for testing and maintenance.
-
Assemblies greater than 2 1/2" shall be supported to protect flange from damage.